Surrey Langley SkyTrain
Check out this dreamy sunrise over the precast concrete facility in @CityofSurrey.🌤️ This facility is where elevated guideway segments are produced and stored.
Surrey Langley SkyTrain tweet media
English
0
0
1
103
Surrey Langley SkyTrain
⚠️Upcoming: Overnight closure of Highway 15 between Fraser Highway and 64 Avenue April 14 – 17, from 12 am – 4 am. Detour routes available. See notification for more info: ow.ly/P9EE50YAUVK Sign up for notifications on our website: ow.ly/L8tc50YAUVL
Surrey Langley SkyTrain tweet media
English
0
0
0
79
Surrey Langley SkyTrain
Crews are building the foundations for the elevated guideway in Langley near Production Way and Fraser Highway! Driven piles are being built into the ground to support the future guideway.
Surrey Langley SkyTrain tweet media
English
0
0
0
138
Surrey Langley SkyTrain
Spring has arrived! Can you spot the similarities between these two?🌷 Tulip columns continue to take shape along Fraser Highway, with more than 60% of the guideway columns now complete. Named for their distinctive form, these columns will support the future elevated guideway.
Surrey Langley SkyTrain tweet media
English
0
0
2
154
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Near 150 Street, an elevated guideway segment is being prepared for installation. Fun fact: one individual segment weighs approximately 28 tonnes!
Surrey Langley SkyTrain tweet media
English
0
0
3
173
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Near Green Timbers Station, the future guideway is starting to take shape. Can you see it down the centre of the Fraser Highway?
Surrey Langley SkyTrain tweet media
English
1
0
2
252
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
You may have noticed wildlife in some unusual places along the Project alignment. Decoy wildlife have been placed throughout the Project area as part of our environmental measures. These fake animals prevent bird nesting on structures during construction!
Surrey Langley SkyTrain tweet mediaSurrey Langley SkyTrain tweet mediaSurrey Langley SkyTrain tweet media
English
0
2
3
217
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Here is an aerial view of Bakerview-166 Street Station. The Fleetwood Flyer has finished building the elevated guideway in this area and is moving west towards 152 Street Station.
Surrey Langley SkyTrain tweet media
English
0
0
3
243
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
The four #SurreyLangleySkyTrain launching gantries that are building the project’s elevated guideway are each more than 100 m long! These specialized lifting machines are installing 4,400+ guideway segments along the alignment. Learn more: ow.ly/v72c50XLN8k
Surrey Langley SkyTrain tweet media
English
0
1
8
1.1K
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
More pieces of rail are arriving in preparation for track installation! The rail is first delivered to a storage area. They will then be transported to the guideway for installation.
Surrey Langley SkyTrain tweet media
English
0
1
5
234
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Following completion of a span, the launching gantry slides over to build the next section of the elevated guideway along the alignment. The launching gantries use the previously constructed columns as support!
Surrey Langley SkyTrain tweet media
English
0
0
2
201
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Crews are installing driven piles using a vibratory hammer as part of ongoing foundation work at the station sites. This unique equipment uses high frequency vibrations to loosen soil particles to drive piles into the ground.
Surrey Langley SkyTrain tweet media
English
0
0
0
183
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
🚧 Elevated Guideway – Step 5: Guideway Once a span is complete, the launching gantry slides over to build the next section of the guideway. Learn more on our website: ow.ly/J7Ao50XLN6a
Surrey Langley SkyTrain tweet media
English
0
0
1
197
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Check out this clip of the Surrey Sprinter lifting a guideway segment into place near 150 St. Did you know that this launching gantry is responsible for lifting 900+ elevated guideway segments into place? Learn more: ow.ly/VzU050YrvtS
English
0
0
4
235
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Fun fact alert 🚨 Each #SurreyLangleySkyTrain elevated guideway span is generally made up of 12 segments between 2 columns. Within station sites, a typical span is made of 5 segments! Need a refresher on what a span is? Check out this post: ow.ly/Zh3e50XmbIm
Surrey Langley SkyTrain tweet media
English
0
0
3
173
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Crews apply a high-strength epoxy, which is a specialized construction glue, to the edges of each segment to join them together. Next, steel cables, also known as tendons, are threaded through the group of segments and pulled tightly, locking them together to form a span.
Surrey Langley SkyTrain tweet media
English
0
0
2
196
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Can you guess what these pipes are for? These pipes are called conduits! The conduits are part of the 16-kilometre underground duct bank that is being built to help power the future SkyTrain. Electrical lines are placed inside the conduits for protection.
Surrey Langley SkyTrain tweet media
English
0
1
2
195
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
Here’s a peek at the inside of a #SurreyLangleySkyTrain elevated guideway span. Spans are made up of guideway segments that are joined together. Cables are threaded through the pipes inside of the segments and then pulled tightly, locking them together to form a span.
Surrey Langley SkyTrain tweet media
English
0
1
3
257
Surrey Langley SkyTrain
Surrey Langley SkyTrain@SLSkyTrain·
🚧 Elevated Guideway – Step 4: Spans After the launching gantries lift the elevated guideway segments into place between the columns, they are joined together to form a section called a span.
Surrey Langley SkyTrain tweet media
English
0
0
0
217