NLHydro@NLHydro·
Producing 824 MW of electrical power, our Muskrat Falls Hydroelectric Generating Station is the second-largest hydroelectric plant in our province. The plant, located on the lower Churchill River in Labrador, has been providing power to Newfoundland and Labrador since 2020. Photo by Hydro employee Brent Marshall #ViewFromHere
NLHydro tweet media
English
1
1
4
730
NLHydro
NLHydro@NLHydro·
Today's Labrador Island Link test was completed successfully with no customer impact. Thank you again for your continued patience as we work to strengthen our electricity system.
English
0
4
12
1.1K
NLHydro
NLHydro@NLHydro·
Labrador Island Link testing will resume this morning. There is always a possibility of customer impact when testing. If there is a power interruption, we are prepared and have supply available to restore customers quickly (typically under 30 minutes). We’ll be monitoring the system closely and will keep you informed as we progress. nlhydro.com/public-advisor…
English
0
4
4
1.5K
NLHydro
NLHydro@NLHydro·
Today's Labrador Island Link test was completed successfully with no customer impact. A second and final test will take place tomorrow pending weather and system conditions. Thank you again for your continued patience. nlhydro.com/public-advisor…
English
0
3
12
1.5K
NLHydro
NLHydro@NLHydro·
Testing of the Labrador Island Link will begin this morning. There is a possibility of customer impact when testing. If there is an outage, we have supply to restore customers quickly (typically < 30 mins). We'll monitor the system and provide updates as we progress. Thank you in advance for your patience. heyor.ca/BFxuuT
English
1
8
7
2.1K
NLHydro
NLHydro@NLHydro·
The 900MW LIL tests previously scheduled for earlier this month will now take place on March 25 & 26. The timing of the tests may change due to weather and system conditions. There is always a possibility of customer impact. If there is an outage, we are prepared and have supply available to restore customers quickly (under 30 mins). We’ll keep you informed of any changes to the testing schedule on our website, Facebook and X. Details: heyor.ca/BFxuuT
English
1
1
1
3.4K
NLHydro
NLHydro@NLHydro·
Stormy weather is on the way for parts of the province. We're monitoring closely and are ready to respond if needed. Take a moment to make sure you’re prepared too with these quick tips. #StaySafe
NLHydro tweet media
English
0
2
2
1.8K
NLHydro
NLHydro@NLHydro·
Update: Power has been restored for customers in Sally's Cove, Cow Head and St. Paul's.  Customers in Rocky Harbour and Norris Point are still without power. Crews are working to remove a tree from the line in that area. Estimated restoration is 11:00.
NLHydro@NLHydro

We are investigating an outage affecting customers in Norris Point, Rocky Harbour, Sally's Cove, St. Paul's and Cow Head this morning, after a line tripped in the area. Restoration time currently unknown. We will update as more details are available.

English
0
4
5
3.7K
NLHydro
NLHydro@NLHydro·
We are investigating an outage affecting customers in Norris Point, Rocky Harbour, Sally's Cove, St. Paul's and Cow Head this morning, after a line tripped in the area. Restoration time currently unknown. We will update as more details are available.
English
0
4
5
3.8K
NLHydro
NLHydro@NLHydro·
Stormy weather is on the way for many areas. Stay safe everyone and follow these quick tips to be prepared in the event of an outage in your community. #nlwx
NLHydro tweet media
English
0
0
2
1.4K
NLHydro
NLHydro@NLHydro·
We’re aware of an outage to approximately 400 customers in Fogo. Very high winds last night resulted in damage to a power line. Crews are on site but we don’t have an estimated restoration time yet. We will provide more information as it becomes available.
English
0
1
1
6.7K
NLHydro
NLHydro@NLHydro·
A mix of wintery conditions occuring all over the province today. Stay safe! A reminder to stay back from downed power lines and immediately call to report. #nlwx
NLHydro tweet media
English
0
4
4
2.9K
NLHydro
NLHydro@NLHydro·
With the myNLhydro app, customers can access account information, receive notifications, outage information, and submit service requests to us anytime, anywhere and on any device. Download our free app today or register at bit.ly/33xn1kb
NLHydro tweet media
English
0
0
1
642
NLHydro
NLHydro@NLHydro·
UPDATE: Hydro Pausing High-Power Testing of the Labrador Island Link The planned high‑power testing of the Labrador Island Link (LIL) scheduled for today has been postponed. Based on current weather forecasts, the test is unlikely to proceed on Thursday, March 12, 2026. During the pre-testing, an issue arose that requires additional time to investigate. This decision is precautionary, and there are no issues with the Labrador Island Link or system reliability. A new date will be scheduled asap and updates will be provided. Thank you for your patience.
English
1
16
16
5K
NLHydro
NLHydro@NLHydro·
On March 10 & 12, Hydro will be testing the Labrador Island Link at 900 MW. There is a possibility of customer impact when testing. If there is an outage, we have supply to restore customers quickly (typically < 30 mins). We'll monitor the system and provide updates as we progress. Thank you in advance for your patience. Learn more: nlhydro.com/public-advisor…
English
1
15
16
6.1K