📍 Site Inspection: ROTARA LSEN School, Carletonville Progress is visible across several structures supporting learners with special educational needs. Momentum has improved, though uneven progress, cash flow challenges, and wet weather continue to impact delivery. 🏗️ Highlights: • Roofing advancing across most structures • Brickwork progressing in key blocks • Electrical works moving through various stages • Sports facilities & roadworks taking shape • Sewer & stormwater connections completed ⚠️ Concerns: • Poor plastering at nutritional centre (redo required) • Quality issues with beam filling • Delays in bulk services approvals 🚧 Next Steps: • Correct defective works • Accelerate electrical installations • Fast-track municipal approvals for water & electricity Work continues on site despite interruptions, with focus on improving momentum and maintaining quality standards. #TacklingG13 #GrowingGautengTogether