The newly completed 4 - cells 3m x 3m box culvert at CH.33+500 along Jebba – Mokwa road in Niger State was awarded to Messrs CGC Nigeria Limited on 25th September, 2025, and substantially completed on 2nd February, 2026.
The above mentioned project. Kindly note that the 4-cell box culvert at CH.33+500 was effectively assessed today May 12, 2026 by the officials of the Niger State field headquarters. It was observed that the box culvert is structurally stable with no visible sign of distress at all.
However, during the assessment, it was observed that the stone pitching on a section of the embankment filling and the concrete chutes experienced settlement and cracked. This is not a serious situation at all.
In response to this, the contractor, Messrs CGC Nigeria Limited, has been directed to open up the crack section on the stone-pitched embankment and reinstate it by tomorow.
Thank you.