Bittractor

5.7K posts

Bittractor banner
Bittractor

Bittractor

@user889889

Entrepreneur, venture investor, strategy trader

Manhattan, NY Katılım Ocak 2016
1.5K Takip Edilen357 Takipçiler
Jay Graham
Jay Graham@JayGNeumark·
@ilzmcfly So why is stock not green big time? What am I missing?
English
1
0
4
379
McFly
McFly@ilzmcfly·
$IREN WHAT DID I DAY? 😱 The Nvidia Deal is confirmed to be 60MW Gross of Capacity by Daniel Roberts That is 75% more than the Microsoft Deal for Air-Cooled B300's instead of Liquid Cooled GB300's This is by far the best neo-cloud deal signed in the market. -> Extremely Lucrative and Profitable deal with 40-50% Profit Margins. -> First neo-cloud deal to include software/fully managed cloud solutions Site: 250MW Air Cooled Childress for 2027 60MW Gross - Annual price per MW Gross: $11.33M 🤯 - ARR: $680M - PUE: 1.45 (Estimate - High end) - Total GPU's: 22,068 (Estimate - High end) - Total GPU costs: $1,544,760,000 for GPU's (Estimate - High end) - Total Retrofit Costs: $4-$5M per MW (Estimate-High end) - Total Retrofit & GPU Cost: $1.785B – $1.845B (Estimate-High end) - Net Profit Range: $1.555B – $1.615 Billion - Net Profit Margin: 45.7% – 47.5% B300's and Air-Cooled Capacity And now confirmed negotiations are underway with Hyperscaler's and Frontier labs for 2027 capacity. Great job to $iren and the Robert Brothers. While other criticize their prior deal this is a extreme improvement and a showcase of their capabilities. Strong deal and strong terms.🚀
McFly tweet media
McFly@ilzmcfly

The 60MW to $NVDA from $IREN seems to be in Gross MW’s Why? IREN says they are deploying the NVIDIA Blackwell chips "within 60MW of existing data center capacity."  "Existing Capacity" is code for "Total Grid Power Available in our old buildings." Thus, the NVIDIA deal is almost certainly 60MW Gross. NVIDIA is hiring IREN to run their internal R&D workloads. This requires a massive software/operator layer (Mirantis) which justifies a much higher price per actual "chip-watt” Standard Air-Cooling PUE: ~1.15 to 1.20. That would mean IT load is more like 51MW which equals $13.33M per MW of IT for B300’s (Nvidia) vs the $9.7M per MW of IT for 200MW IT of B300’s (Microsoft) That would be a 37.42% Increase from the Microsoft deal 😱 In the 1-3 pictures attached you can clearly see that they refer to “existing data center capacity” as MW gross. Math: 150MW Gross referred to as 100MW IT in the second slide. 250MW existing capacity is gross because 250MW + 150MW/100MW IT= 400MW Gross left available at Childress Childress is 750MW Gross: 350MW Contracted + 400MW Available = 750MW Childress: 290MW Gross - Microsoft (LC) 60MW Gross - Nvidia (AC) 150MW - Liquid Cooled (LC) 250MW - Air Cooled (AC)

English
23
41
446
85.7K
Perry Lin
Perry Lin@perry_lin1·
$WULF After some communication with the @TeraWulfInc team, I was informed that there were only positive intervenors (KY AG and Gov is supportive) who filed by the May 20 deadline as stipulated in the order. psc.ky.gov/order_vault/Or… Given the lack of opposition, they expect the timeline for approval to be accelerated. Justified Data Campus is happening and a customer lease is on the way.
English
15
17
128
9.1K
matthew sigel, recovering CFA
matthew sigel, recovering CFA@matthew_sigel·
$WULF turns higher +4% pre Despite no news/slight miss on press release, couple slightly optimistic anecdotes from call moving stock up >Q1 HPC gross margins were 50% vs LT guidance of 85% for HPC, but broke down several one-timers that get you back to 85%$2.1M of tenant fit our rev and costs during 1Q >$3.5M of pre-rev operating costs at WULF compute >$2.1M of dev costs across 1.75GW portfolio of uncontracted dev site >Adjusting yields 85% segment profit margin Expects the Kentucky customer to be signed in 2Q (480MW) to be "investment grade super high quality"; hinted at expansion beyond the initial site. Sounds like it was very competitive process and should expect 'favorable pricing terms' $WULF
English
9
8
94
8.5K
Bittractor
Bittractor@user889889·
@MktMavPro NVDA took a call option, not just a direct investment yet. but still, big leap forward for IREN.
English
0
0
1
236
MarketMaverick
MarketMaverick@MktMavPro·
$IREN falling hard from that spike... Did someone read the fine print? What's happening?
English
63
0
286
137.2K
Antonio Costa
Antonio Costa@ACInvestorBlog·
Huge news for $IREN NVIDIA and IREN Announce Strategic Partnership to Accelerate Deployment of up to 5 Gigawatts of AI Infrastructure $NVDA When $100 ? In May or June ?
Antonio Costa tweet media
English
5
5
37
5.3K
DVB
DVB@DeepValueBagger·
I'm so close to 10m guys. But I'm not celebrating or changing my bio yet. I want to see it settle out for a few weeks, and my goal is to get this over $10m post-tax. I'm happy nevertheless!
DVB tweet media
English
97
14
774
95K
Bittractor
Bittractor@user889889·
@HenriVisne35246 @Alex83110581 With KY site signed, yes. Then CIFR will have OH site for 2nd half and big pipelines coming by July of ecort decision. Both are executing very well, tight race.
English
0
0
1
33
Alex
Alex@Alex83110581·
Is $WULF truly worth $3 billion more in market cap than $CIFR?
English
5
0
5
9.1K
Bittractor
Bittractor@user889889·
@accounting_ds the first one to sign a direct deal w/ a hyperscaler, and have more diversified clients among miners, that’s why they have better rates in debt mkt comparing to others, even comparing to wulf. Once they convert MW to revenues, that’s the real inflection pt comes, execution is key
English
0
0
2
46
Daniel S
Daniel S@accounting_ds·
@user889889 You understand more than me, which is why I value your opinion greatly, you mentioned the bond markets before, and the pricing miss match between equities Gonna look into that more
English
1
0
1
194
Daniel S
Daniel S@accounting_ds·
Its very important to understand what you own, especially for a company like $CIFR And not in the tacky way to rally the bulls, in the understanding how valuation works inside this specific ecosystem: power, sites, financing, tenant commitments, construction timelines, and when revenue actually begins to show up kind of way That’s why obsessing over a “double miss” here feels low signal to me We now need to collectively view $CIFR as a landlord company mid transition before major AI/HPC tenants start contributing meaningfully to the income statement, that backwards historical data is counting Odessa mining economics and a few other legacy pieces, not the full forward model investors are underwriting I am not posting this to dunk on anyone, I have lost a lot of money playing different sectors I did not comprehend, for example Space, I make a lot more focusing on what I know and am passionate about, for me that is Energy, intercorrelated with AI and its buildout
HumzyTrades@HumzyTrades

How tf is $CIFR 10% up even after missing earnings A whole lotta stuffs not adding up in this markets lol

English
7
3
91
16.3K
Bittractor
Bittractor@user889889·
@HagenMikkel_ @SylentTrade Yes, they announced that weeks ago, but today we learned that the price /mw is 15% higher. Plus, all projects on time, just a few months away.
English
0
0
2
108
Sylent Capital
Sylent Capital@SylentTrade·
$CIFR just announced they signed another deal with a hyperscaler during their earnings this morning. Don’t be surprised when $IREN announces a deal on their earnings call this thursday afternoon.
English
4
12
358
24.2K
Daniel S
Daniel S@accounting_ds·
@user889889 Execution has been phenomenal and leadership speaks with such confidence and integrity, excited to see them execute
English
1
0
1
75
Daniel S
Daniel S@accounting_ds·
$CIFR is in a very fascinating spot Cipher Digital marked the official business model switch, this operation is no longer even slightly correlated to $BTC mining So now, a public company is undergoing a model change while staying public, how can we accurately forecast numbers when backwards looking data does not support the current mission of the company? That exact inflection is where I believe significant Alpha exists You are putting money on the team, an idea, and execution Execution has been flawless thus far, and if it continues to be, when revenues actually begin to transform the income statement and ERCOT confirms a larger pipeline, a much stronger forecast can be made So do you think they will be worth more than 7B by then, with 11B already contracted Seems fairly obvious to me🤷🏻‍♂️
Daniel S@accounting_ds

$CIFR business update ~ Barber Lake is still on schedule✅ Black Pearl Phase I retrofitting is underway, and Phase II site/layout work began in April✅ Third AI data center campus lease with an investment grade hyperscale tenant✅ $200M corporate revolver, which gives them more liquidity and flexibility to fund the equity portion of the third campus and near term capital needs✅ $CIFR is still on timeline, still attracting hyperscale tenants, and still finding capital to fund the buildout Let’s hear what Tyler has to say, feeling very good about the business update investors.cipherdigital.com/news-releases/…

English
4
6
92
10.2K
Bittractor
Bittractor@user889889·
@MktMavPro On time delivery is everything. 700m just a few mth away.
English
0
0
1
286
MarketMaverick
MarketMaverick@MktMavPro·
$CIFR - love the confidence in this CEO…
English
8
4
144
6.1K
Bittractor retweetledi
Neil Bhatia
Neil Bhatia@neilsbhatia·
Good Morning All - As below: $DGXX goes BOOM. Who is next this week I query? $SOUN $IMSR $SHMD $CNTMD ? My Names: $AMZE $INTC $MU $DGXX $GLXY $RKLB $BMNR $EOSE $LAES $SHMD $BABA $CNTMD $ABVE $DFNS $KZIA $TOYO $TE $AMPX $PHGE $IMSR $RDDT $SOUN $SIDE (on watch for initiation)
Neil Bhatia@neilsbhatia

If Lively/Baldoni can do it … Iran mustn’t be far … As I said this morning: $SOUN $IMSR $SHMD $DGXX $CNTMD … in no particular order …

English
1
2
7
116.5K
Bittractor
Bittractor@user889889·
@accounting_ds Possible if they get 3M approval by July and market them for 2027.
English
0
0
0
20
Daniel S
Daniel S@accounting_ds·
So I actually think $61 is still very possible in 2026 $CIFR reports next week and I am eager to see the report I think we may be entering an environment again where you can throw a dart at the DC wall and won’t go wrong Unless…that dart lands on $MARA😅
Daniel S@accounting_ds

$CIFR 2026 Price Prediction Revised 🚨 As new information has come out in Q3 and the fundamentals have only gotten stronger, I have the urge to redo my prediction and bring a whole new level of sophistication With this current drawdown as well, $CIFR at $14.36 with a market cap of $5.67 billion has become the most compelling opportunity in the market today So let's begin… Part 1 HPC 🏭~ At $366.7 million in annual revenue over the 15 year term, the $AMZN contract generates approximately $1.22 million per MW annually At $300 million annually in base revenue over the 10-year term, the contract generates approximately $1.79 million per MW Combined, the AWS and Fluidstack contracts represent $8.5 billion in total contracted revenue a figure that exceeds $CIFR entire current market capitalization and provides unprecedented visibility into future cash flows $CIFR unveiled the formation of a joint venture to develop “Colchis,” a 1 gigawatt data center site in West Texas Under the joint venture terms, $CIFR will provide the majority of financing, resulting in approximately 95% equity ownership assuming standard lease and development terms At scale, Colchis represents transformational value creation assuming similar revenue economics to the AWS and Fluidstack deals (approximately $1.50 million per MW annually) Beyond Colchis, $CIFR maintains an extensive development pipeline totaling 3.2 GW of site capacity 300 MW: Allocated to AWS contract 244 MW: Allocated to Fluidstack/Google contract 1,000 MW: Colchis development 1,656 MW: Remaining unallocated capacity for future opportunities Using conservative industry valuations of $10 million per MW for development sites with secured power agreements, a standard benchmark for data center M&A transactions, this pipeline carries an embedded value of approximately $16.6 billion I will do all the math once we go over the next section Part 2 $BTC Mining ⛏️ ~ As of Q3 2025, the company operates at 23.6 EH/s of self-mining hashrate across five industrial-scale data centers, having successfully completed the energization of its flagship Black Pearl Phase I facility The company deployed 114,000 mining rigs by September 2025, with fleet efficiency of 16.8 J/TH, positioning it as one of the most energy efficient miners in North America🇺🇸 As of September 30th $CIFR maintains a strategic Bitcoin treasury position of 1,500 BTC Valued at approximately $171 million at current prices but worth $262 million at the assumed $175,000 $BTC price Which leads to my next point: I will be lowering my $BTC PT from 200 to 175 to make this more “reasonable,” as right now 200k implies over a 100% move, which I think can happen but I wont put my Giga bull bias into this and will keep it at 175k Part 3 Calculation 📚~ MINING OPERATIONS (23.6 EH/s) 📊 Current hashrate: 23.6 EH/s Annual production calculation: Q3 2025 production: 689 $BTC Quarterly baseline × 4 = 689 × 4 = 2,756 BTC Annual production: 2,756 BTC baseline with a potential 2× hashrate boost from efficiency gains: 2,756 BTC × 2 = 5,512 $BTC per year Mining Revenue = 2,756 BTC × $175,000 = $482,300.00 Profit margins: Energy cost ≈ $0.027/kWh Energy cost per $BTC ≈ $17,000 Since energy cost ≈ $17,000/BTC or ~$0.027/kWh Profit margins: 72.5% (industry-leading efficiency) Mining Profit = $482,300,000 × 0.725 = $349,667,500 Mining Business Valuation: $349.7M profit × 8x EBITDA = $2.80 billion HPC 📈 - AWS/ ( $AMZN ) Contract value: $5,500 million over 15 years Annual revenue = $5,500M ÷ 15 = $366.7M Gross Capacity: 300 MW NOI margin = 82.5% Annual NOI = $366.7M × 0.825 = $302.5M profit CapEx: $10M per MW Total CapEx = 300 MW × $10M = $3,000M total investment Implied payback = $3,000M ÷ $302.5M = 9.9 years ROI = 10.1% per MW annually Valuation: 20× EBITDA (contracted HPC premium) = $302.5M × 20 = $6.05 billion HPC 📈 - Fluidstack/ ( $GOOGL ) Contract value: $3,000 million over 10 years Annual revenue = $3,000M ÷ 10 = $300M IT Load Capacity: 168 MW NOI margin = 82.5% Annual NOI = $300M × 0.825 = $247.5M profit CapEx: $10M per MW Total CapEx = 168 MW × $10M = $1,680M total investment Implied payback = $1,680M ÷ $247.5M = 6.8 years ROI = 14.7% per MW annually Valuation: 20× EBITDA (contracted HPC premium) = $247.5M × 20 = $4.95 billion TOTAL HPC (Contracted): Annual Revenue: $666.7M Annual NOI: $550.0M Total Valuation: $11.00B A 20x EBITDA multiple is well supported and likely conservative for $CIFR contracted hyperscale/AI hosting platform, given the premium paid for long-term, investment-grade, and mission-critical data center deals in the current market environment Colchis Development (1,000 MW) 🏗️ Capacity: 1,000 MW Ownership: 95% (JV structure) Additional capacity: 1,000 MW (in addition to the 468 MW) Revenue per MW (avg of deals): Fluidstack: $300M ÷ 168 MW = $1.79M/MW AWS: $366.7M ÷ 300 MW = $1.22M/MW Average: $1.50M per MW Annual revenue per MW: $1.50M Colchis revenue = 1,000 MW × $1.50M × 0.95 = $1,428.8M Annual NOI per MW: $1.24M Colchis NOI = $1,428.8M × 0.825 = $1,178.7M Total additional revenue: $1,428.8 million per year Total CapEx required: 1,000 MW × $10M = $10,000M = $10.0 billion Valuation multiple: 14× (development discount from 20×) Note: 30% discount for development risk and 2028 timeline Undiscounted value = $1,178.7M × 14 = $16,502M = $16.50 billion Present Value Calculation: Energization: 2028 (2.5 years) Discount rate: 10% Discount factor = 1 ÷ (1.10)^2.5 = 0.7880 PV = $16.50B × 0.7880 = $13.00 billion 1,000 MW × $1.50M/MW × 95% ownership × 82.5% margin × 14x multiple × 0.788 discount = $13.0B Just thought I would put the equation up there, as this was the hardest part to calculate Additional Pipeline (1,656 MW) 🚀 Total development pipeline: 3,200 MW = 3.2 GW Allocated: Remaining unallocated: 3,200 - 1,544 = 1,656 MW Pipeline valuation: $10M per MW (development site value) Industry standard for sites with secured power Total pipeline value = 1,656 MW × $10M = $16,560M = $16.56 billion Probability adjustment for development pipeline: Base case applies 70% probability to reflect: -Site development risks -Tenant leasing uncertainty -Longer time horizon Probability-adjusted value: $16,560M × 70% = $11,592M = $11.59 billion Treasury $BTC in holding 💰 Holding: 1,500 $BTC Price assumption: $175,000 per $BTC Treasury value = 1,500 BTC × $175,000 = $262,500,000 = $262 million TOTAL ENTERPRISE VALUE (Sum of All Parts): Mining Business: $2.80B HPC Contracted (AWS+FLS): $11.00B Colchis Development (PV): $13.00B Additional Pipeline (70%): $11.59B Bitcoin Treasury: $0.26B TOTAL EV = $2.80B + $11.00B + $13.00B + $11.59B + $0.26B = $38.65 billion Adjustments: Convertible Notes Outstanding: $1,300M Terms: 0.00% interest, due 2031 Conversion price: ~$16.03 Capped call protection at $23.32 Effective net debt treatment: $1,300M × 50% = $650M (Conservative: treat as 50% debt / 50% equity equivalent) Enterprise Value: $38,654.84M Less: Net Debt: -$650M Equity Value: $38,004.84M = $38.00 billion Basic shares outstanding: 395 million Dilution from convertible notes: Potential new shares: $1,300M ÷ $16.03 = 81.1M shares Less: Capped call reduction (~40%): -32.4M Net dilution: 48.7M shares Fully diluted shares = 395M + 48.7M = 444 million shares VALUATION PER SHARE: Equity Value ÷ Shares = $38,004.84M ÷ 444M = $85.66 per share (UNRISKED) Risk Adjustment: Probability weighting for execution and market variables: 75% Risk factors considered: -Colchis development execution (2028 timeline) -ERCOT interconnection approval -Tenant leasing for remaining pipeline - $BTC price realization -Energy market dynamics -General market conditions Risk-adjusted calculation: $85.66 × 0.75 = $64.25 per share As you can see that is some serious upside... we are CRIMINALLY priced right now The future has never been brighter; if price action and drawdowns scare you, do more research and reassess your conviction Let me know what you think about this calc and prediction! thank you so much if you got this far :)

English
7
3
39
8.6K
Bittractor
Bittractor@user889889·
@accounting_ds CIFR should trade at higher NOI than the rest due to their client base, this is already reflected in the debt mkt but not in equity mkt yet.
English
0
0
0
35
Daniel S
Daniel S@accounting_ds·
I think Im done trading in and out, that's what fucked my $7 basis, also Cipher is so emotionally draining to trade that I will just continue to quietly accumulate at reasonable levels, not too much to talk about on a daily basis with them anymore, pretty crystal clear they will be successful as long as things stay on course
English
1
0
2
73
Daniel S
Daniel S@accounting_ds·
Food for thought on $CIFR Delivery begins in September this year, which should not only begin to transform their income statement but also optically validate their thesis After the October run, it was fair to say valuation was a little rich at $25 However, after some nice business updates and confirmation of CoLo business model, its hard to say their not undervalued here Q4 is when Black Pearl begins to deliver as well Been better places to be this past 6 months but the time is near again Sort of hard to be structurally bearish any DC stock with S tier clients and recurring revenue, we truly have a compute crisis in a time where somehow Data Centers have become political martyrs
Cipher Digital@CipherInc

Cipher is pleased to announce the following business updates: - Execution of a new 15-year data center campus lease with Hyperscale tenant - Closing of $200m revolving credit facility, supported by leading global financial institutions Read the full press release here: investors.cipherdigital.com/news-releases/…

English
8
11
116
39K
Bittractor
Bittractor@user889889·
@accounting_ds Hard to predict short term movements. CIFR WULF are good long term investments though. Price movements still volatile, but you can earn extra from selling calls.
English
1
0
1
47
Daniel S
Daniel S@accounting_ds·
@user889889 You have always been a great voice of reason and someone with a very nice cost basis Any predictions for this week across the board? I am thinking many of these companies will move in a pac
English
1
0
0
183