Stenukäsi

143 posts

Stenukäsi

Stenukäsi

@Stenustian

Katılım Kasım 2025
119 Takip Edilen18 Takipçiler
Stenukäsi retweetledi
XCap
XCap@XCapitalMgmt·
$IREN bear thesis progression on Sweetwater 1. Energization debate settled. Next debate (deal or no deal and on what terms) is for all the marbles.
XCap tweet media
English
14
14
226
11.7K
Stenukäsi retweetledi
Sijottelija
Sijottelija@UnnajaSnoop·
Unless western traders have huge stockpiles of tungsten (which I believe they don’t) - I just don’t see what market mechanism could bring western tungsten prices down. The western supply gap should be over 20kt - Sangdong at full phase 1+2 is less than 5kt. When supply
English
2
2
19
600
Stenukäsi retweetledi
IREN
IREN@IREN_Ltd·
Sweetwater 1 has been successfully energized – a key milestone in the development of the broader 2GW Sweetwater campus. @danroberts0101, Co-Founder and Co-CEO of $IREN commented: “Delivering Sweetwater 1 substation energization on schedule reflects our disciplined execution, the strength of our supply chain relationships and the efficiency of our vertically integrated development model. It is another example of our ability to design and construct large-scale infrastructure reliably and at speed to meet market demand.” Learn more: iren.gcs-web.com/static-files/d…
English
158
495
3.5K
646.3K
Stenukäsi retweetledi
Frans Bakker
Frans Bakker@FransBakker9812·
"The winners under this regime are whoever locked in power purchase agreements and electrical equipment orders 3-4 years ago, before anyone was modeling hundreds of megawatts of inference load. Everyone else is waiting in line behind them." $IREN fixes this 🏗️ SW1 4/26/2026 ⤵️
Frans Bakker tweet media
Aakash Gupta@aakashgupta

A 5-year backlog on grid transformers just killed half of America's 2026 AI data centers. Sightline Climate tracked 12 GW of 2026 US data center capacity announced across 140 projects. Only 5 GW is actually under construction. 11 GW sits in the "announced" stage with no physical progress despite typical build times of 12-18 months. 25% of those projects haven't disclosed a power strategy at all. That last number is the tell. A quarter of "planned 2026 AI capacity" has no sourced answer to where the electrons come from. Call those projects what they are: vapor capex with a press release attached. Nvidia is shipping. The gating constraint is high-voltage transformers, switchgear, and grid-tie batteries. Pre-2020 lead time on a high-power transformer was 24-30 months. Today it stretches to 5 years. Electrical equipment is under 10% of total data center cost and 100% of the bottleneck. This breaks the standard analyst model. When a hyperscaler announces $50B of capex, the Street treats it as compute coming online in 18 months. If the transformer order wasn't placed in 2022, that money sits as commitment without capacity. You cannot pay for a transformer that doesn't exist yet. The winners under this regime are whoever locked in power purchase agreements and electrical equipment orders 3-4 years ago, before anyone was modeling hundreds of megawatts of inference load. Everyone else is waiting in line behind them. Second order is uglier. Hyperscalers buying $50B of GPUs that sit unpowered depreciate against Nvidia's annual cadence while paying carrying costs on empty data center shells. Every quarter dark is a quarter of compounding waste. The "we're 6 months from running out of compute" panic just became "we're 5 years from running out of transformers." Capital fixes one. Capital cannot manufacture a transformer.

English
39
72
528
107.3K
Stenukäsi
Stenukäsi@Stenustian·
@Edark94 Do you believe the western supply/demand gap has significantly narrowed, or what would drive the decline of prices in the near future?
English
1
0
2
146
Emil Baggie.tinkaren
The unfort thing is that the market is pricing in insane prices with no basis of reality. May I remind y'all prices were around 400/MTU for years prior to this rally... $2-3000 is insane squeeze territory, not sustainable at all. $1000/MTU floor until 2030 is my expectation.
English
3
0
11
1.4K
Emil Baggie.tinkaren
Unfortunately, the site visit sell off already occured. Right now, I'd wager the hot money chasing #tungsten is a bit frightened about the top seen in China. Normally, ROW won't be far behind. Wouldn't surprise me, but am expecting prices to find a floor well above $1000/MTU
Emil Baggie.tinkaren tweet media
Alexsei@Alexsei88

Jaaha, onkohan EQ Resourcesin kaivoksilla pidetty taas vierailukäynti suuremmille sijoittajille? Päässyt isokenkäiset katsomaan tulvien vaikutuksia ja nyt on taas lappuja myyty laitaan? Mielestäni tuollaiset vierailutkin voitaisiin lopettaa kun kaivokset on ongelmissa. $EQR.AX

English
4
0
20
6.5K
Stenukäsi retweetledi
Pekka K
Pekka K@88_becks·
🔥BOOOM🔥 Breaking: $EQR.AX set to bring Wolfram Camp online! ⛏️ With tungsten prices skyrocketing, adding a THIRD production asset is a game changer. The 'Perfect Storm' just got even more intense. This is what we've been waiting for! #tungsten
Sijottelija@UnnajaSnoop

Quartr sovelluksen tiivistelmä tulospuhelun transkriptistä: EQ Resources — Q3 FY2026 webinar key takeaways Tungsten market •APT low-price reached $2,800/MTU at end of March 2026, up ~240% quarter-on-quarter and ~700% year-on-year from US$350/MTU in March 2025. •The average low price for the quarter was US$1,874/MTU. •Chinese export controls continue; top 5 Chinese state-owned producers reportedly made record profits in 2025 with no incentive to change behaviour. •Management estimates a customer order backlog that will take 8–9 months to work through. Barruecopardo (Spain) — operations •Q1 2026 was almost certainly the wettest first quarter since 1979 in Salamanca province, with 110% above-normal precipitation in January–February. •Production was negatively impacted by ~50% compared to the December quarter. •~1.9 metres of water accumulated at the pit base (highest-grade zone: 1 million tonnes at 0.2% WO3 or better), reduced to ~1.5 metres by report date. •16,000 cubic metres of water sitting in the pit; Spanish government approval sought for a discharge of up to 12,000 m³. RO plants being procured for treatment and discharge. •Spanish regulators approved installation of an additional outsourced crushing unit to increase volume to TOMRA ore sorters. •Spanish debt reduced by €1.5 million to €15 million and refinanced over a 3-year period at 1-month Euribor + 5.5% (7.4% at 31 March 2026). •Phase 1 drilling program of 37 holes / ~12,200 metres planned at Barruecopardo (ore body open to north, south, east and depth); drilling expected to commence in ~2 months. Phase 2 and 3 follow-on possible. •Only 45% of the Barruecopardo resource has been converted to reserve. Mount Carbine (Australia) — operations •Record material movement of 821,678 tonnes for the quarter despite wet-season impacts. •Access to the high-grade Iolanthe vein system commenced in the last week of March 2026, about 6 weeks behind plan. •April 2026 production at Carbine expected to exceed the entire March quarter output in a single month. •Target ramp-up to 10,000–12,000 MTU/month, with an aspiration to reach 1,750 tonnes/year (WO3) in calendar 2026, then 2,500 tonnes with full access to the large vein system. •Crushing circuit expansion targeting completion by February 2027: doubling capacity from ~87,000 t/month to ~170,000–180,000 t/month; expected to lower operating costs by ~30% per tonne processed. •Expansion also incorporates significantly more automation, reducing the number of times each tonne of rock is handled from 13 times to 3–5 times. •Currently only one ore face operating; plan to open multiple faces (target 3–4) to de-risk against weather and technical stoppages. •New Queensland mines inspectorate lightning regulation increased the exclusion zone from 17 km to 30 km, causing additional downtime; mitigation works planned for the dry season. Wolfram Camp exploration •Rigs planned to relocate from Carbine to Wolfram Camp around mid-July 2026 to convert the historical non-JORC resource to JORC standard. •Queensland Government indicated an ML could be approved within 12 months; management considers 18 months more realistic. •Plan to mine, crush and sort material at Wolfram Camp for processing at Carbine’s excess gravity circuit capacity. Financials & balance sheet •Revenue of AUD 32.7 million for Q3 FY2026; cash receipts of AUD 19.8 million after prepayment reductions of AUD 6.9 million and a AUD 5.9 million increase in accounts receivable. •Cash on hand at 31 March 2026: AUD 15.5–15.8 million; accounts receivable: AUD 15 million. •Cash on hand reported as approximately AUD 22 million as at the date of the webinar (29 April 2026). •Oaktree debt of AUD 7.25 million fully converted to equity following shareholder approval in March 2026. •Net cash outflow from operations was AUD 11.5 million in Q3 FY2026, driven by weather-impacted production and timing of shipments. •Management stated no further capital raising is anticipated in the near term. Corporate & governance •Michael Nossal appointed Independent Non-Executive Chairman effective 1 April 2026. •New hires: General Counsel (Virna Trout), Group IT Manager, Group Reporting Manager (starting the day of the webinar). •5-year Brisbane CBD office lease entered, commencing 1 June 2026. •Management and CFO have spent ~80 hours in investor meetings, with strong inbound from US and European institutions (4–6 US investor meetings per week between the two of them). •Nasdaq listing is being reviewed but not imminent; US investors reported they can access EQR on the ASX. An LEI has been obtained to facilitate European (e.g., German) institutional purchases. •Tungsten Metals Group potential acquisition still under discussion; no decision reached, update promised “in due course.” Weather risk mitigation plan •Plan to build 2-month ROM pad stockpiles at both sites (Barruecopardo and Carbine) to decouple mining from processing during wet seasons; estimated cost AUD 2–4 million per site

English
2
8
64
6K
Stenukäsi retweetledi
Sijottelija
Sijottelija@UnnajaSnoop·
Quartr sovelluksen tiivistelmä tulospuhelun transkriptistä: EQ Resources — Q3 FY2026 webinar key takeaways Tungsten market •APT low-price reached $2,800/MTU at end of March 2026, up ~240% quarter-on-quarter and ~700% year-on-year from US$350/MTU in March 2025. •The average low price for the quarter was US$1,874/MTU. •Chinese export controls continue; top 5 Chinese state-owned producers reportedly made record profits in 2025 with no incentive to change behaviour. •Management estimates a customer order backlog that will take 8–9 months to work through. Barruecopardo (Spain) — operations •Q1 2026 was almost certainly the wettest first quarter since 1979 in Salamanca province, with 110% above-normal precipitation in January–February. •Production was negatively impacted by ~50% compared to the December quarter. •~1.9 metres of water accumulated at the pit base (highest-grade zone: 1 million tonnes at 0.2% WO3 or better), reduced to ~1.5 metres by report date. •16,000 cubic metres of water sitting in the pit; Spanish government approval sought for a discharge of up to 12,000 m³. RO plants being procured for treatment and discharge. •Spanish regulators approved installation of an additional outsourced crushing unit to increase volume to TOMRA ore sorters. •Spanish debt reduced by €1.5 million to €15 million and refinanced over a 3-year period at 1-month Euribor + 5.5% (7.4% at 31 March 2026). •Phase 1 drilling program of 37 holes / ~12,200 metres planned at Barruecopardo (ore body open to north, south, east and depth); drilling expected to commence in ~2 months. Phase 2 and 3 follow-on possible. •Only 45% of the Barruecopardo resource has been converted to reserve. Mount Carbine (Australia) — operations •Record material movement of 821,678 tonnes for the quarter despite wet-season impacts. •Access to the high-grade Iolanthe vein system commenced in the last week of March 2026, about 6 weeks behind plan. •April 2026 production at Carbine expected to exceed the entire March quarter output in a single month. •Target ramp-up to 10,000–12,000 MTU/month, with an aspiration to reach 1,750 tonnes/year (WO3) in calendar 2026, then 2,500 tonnes with full access to the large vein system. •Crushing circuit expansion targeting completion by February 2027: doubling capacity from ~87,000 t/month to ~170,000–180,000 t/month; expected to lower operating costs by ~30% per tonne processed. •Expansion also incorporates significantly more automation, reducing the number of times each tonne of rock is handled from 13 times to 3–5 times. •Currently only one ore face operating; plan to open multiple faces (target 3–4) to de-risk against weather and technical stoppages. •New Queensland mines inspectorate lightning regulation increased the exclusion zone from 17 km to 30 km, causing additional downtime; mitigation works planned for the dry season. Wolfram Camp exploration •Rigs planned to relocate from Carbine to Wolfram Camp around mid-July 2026 to convert the historical non-JORC resource to JORC standard. •Queensland Government indicated an ML could be approved within 12 months; management considers 18 months more realistic. •Plan to mine, crush and sort material at Wolfram Camp for processing at Carbine’s excess gravity circuit capacity. Financials & balance sheet •Revenue of AUD 32.7 million for Q3 FY2026; cash receipts of AUD 19.8 million after prepayment reductions of AUD 6.9 million and a AUD 5.9 million increase in accounts receivable. •Cash on hand at 31 March 2026: AUD 15.5–15.8 million; accounts receivable: AUD 15 million. •Cash on hand reported as approximately AUD 22 million as at the date of the webinar (29 April 2026). •Oaktree debt of AUD 7.25 million fully converted to equity following shareholder approval in March 2026. •Net cash outflow from operations was AUD 11.5 million in Q3 FY2026, driven by weather-impacted production and timing of shipments. •Management stated no further capital raising is anticipated in the near term. Corporate & governance •Michael Nossal appointed Independent Non-Executive Chairman effective 1 April 2026. •New hires: General Counsel (Virna Trout), Group IT Manager, Group Reporting Manager (starting the day of the webinar). •5-year Brisbane CBD office lease entered, commencing 1 June 2026. •Management and CFO have spent ~80 hours in investor meetings, with strong inbound from US and European institutions (4–6 US investor meetings per week between the two of them). •Nasdaq listing is being reviewed but not imminent; US investors reported they can access EQR on the ASX. An LEI has been obtained to facilitate European (e.g., German) institutional purchases. •Tungsten Metals Group potential acquisition still under discussion; no decision reached, update promised “in due course.” Weather risk mitigation plan •Plan to build 2-month ROM pad stockpiles at both sites (Barruecopardo and Carbine) to decouple mining from processing during wet seasons; estimated cost AUD 2–4 million per site
Suomi
8
8
78
15.1K
Stenukäsi retweetledi
Alexsei
Alexsei@Alexsei88·
Arvioidaan EQ Resourcesin markkina-arvoa ja liikevaihtoa; 🔸320,000 MTU vuosituotanto 🔸EQR:n saama hinta myymästään rikasteesta 2,000 USD/MTU Liikevaihto 320,000 x 2000 =640m USD =0.64b USD. Jos verrataan tähän listaan, olisiko EQR:n 10b markkina-arvo paha? $EQR.AX
Alexsei tweet mediaAlexsei tweet media
Suomi
3
4
65
7.2K
Stenukäsi retweetledi
Sijottelija
Sijottelija@UnnajaSnoop·
@Alexsei88 Porukka puhuu että Sangdong helpottaa vajetta. No, kyllä se vähän helpottaa, mutta eipä semmonen vajaa 5000 tWO3 (phase 1 + 2) meitä pelasta, kun vaje on liki 80’000 tWO3.
Sijottelija tweet media
Suomi
1
2
14
682
Stenukäsi retweetledi
Alexsei
Alexsei@Alexsei88·
@BlackScholesMan Good evening from Finland! 🫡 EQ Resources is the largest tungsten producer in the West, larger than Masan, with its two mines located in Australia and Spain. #Tungsten $EQR.AX 🔗
English
1
4
82
6.3K
Stenukäsi retweetledi
EQ Resources Limited
EQ Resources Limited@EQResourcesASX·
⛏️ EQR (ASX:EQR) has commenced a Mt Carbine drilling program to support resource extensions, reserve definition & future mine planning. • 28 holes / ~7,700m • DD started 16 Mar (5 holes/1,900m); RC mobilised 11 Apr (3 holes/710m) • Targets: Bluff, Dazzler, Iolanthe, Johnson, Ruby, Iron Duke • Assays (Intertek) 20–30 business days; results over 3–6 months 🔗 eqresources.com.au/site/showdownl… #EQR #Tungsten #CriticalMinerals #ASXNews #MiningNews
EQ Resources Limited tweet mediaEQ Resources Limited tweet media
English
3
31
157
10K
Alexsei
Alexsei@Alexsei88·
@JarmoFriman Jännä että NASDAQ-listattu Swarmer puuttui tuolta listalta. Ukrainalainen droneyhtiö. Suuri markkina-arvo suhteessa talouslukuihin, mutta niinhän se kaikilla tämän alan teknofirmoilla. $SWMR
Suomi
1
0
5
1K
Stenukäsi retweetledi
Alexsei
Alexsei@Alexsei88·
Mt. Carbinella on ollut kairaukset käynnissä jo useamman viikon. Lisäksi Iolanthen malmi on nyt saavutettu ja se on ollut tuotannossa jo pidemmän aikaa, tämäkin on nyt virallisesti ilmoitettu, jollei sitä vielä ollut tiedotteella kerrottu. #Tungsten $EQR.AX
Alexsei tweet media
Suomi
1
6
78
9.3K
Stenukäsi retweetledi
Miikkael
Miikkael@el_miikka·
Sandvik 26 Q1 Earnings Call. Market dynamics are already changing as some #tungsten cutting tool suppliers are not able to supply due to limited access to tungsten. Sandvik has a secured supply chain, so they'll pay whatever and grab those market shares.
Miikkael tweet media
English
0
1
13
3.4K
Stenukäsi retweetledi
Euroz Hartleys
Euroz Hartleys@EurozHartleys·
Euroz Hartleys James McClements & Michael Scantlebury recently visited EQ Resources Limited's Mt Carbine tungsten mine in North Queensland. With spot tungsten prices (~US$2,800-3,280/mtu), EQR on our numbers is generating annualised free cash flow of ~A$500m from the JunQ forward. Thank you to the @EQResourcesASX team for hosting our Euroz Hartleys representatives on site. #Mining #Resources #Tungsten #ASX
Euroz Hartleys tweet mediaEuroz Hartleys tweet media
English
18
39
214
94.8K
The Market Matrix
The Market Matrix@MarketMatrixs·
Stocks that could double from here and still be relatively undervalued: 1. $ASTS 2. $ADUR 3. $OSCR 4. $ZETA 5. $PATH 6. $SOFI 7. $RKLB 8. $IREN 9. $NBIS 10. $EOSE 11. $HIMS 12. $GOOGL Anything else..?
English
21
13
150
13.6K
Stenukäsi retweetledi
𝐀𝐠𝐫𝐢𝐩𝐩𝐚 𝐈𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭𝐬
As it relates to $IREN, your facts and conclusions are off, Daniel. $IREN did in fact start developing "AI data centers" as early as 2021, when breaking ground in Prince George & Mackenzie (Canada). Technically, you could even go as far back as 2019, when you take into account the company's first site 'Canal Flats', partially developed by PodTech, a data center company $IREN merged with in early 2020. You are conflating a few things... Yes, $IREN's first batch of H100 GPUs, did not get installed until February 2024, but the underlying data center infrastructure already existed many years prior. While that infrastructure was initially purposed to mine $BTC, it was always over-specced for that singular purpose (much more expensive & durable than traditional mining data centers). Since day 1, management positioned itself as a disruptive data center company. Mining $BTC was merely the easiest path forward to monetize its powered-land portfolio quickly & scale its data center footprint at rapid speeds. As such, the facilities were always designed to be modular and multi-purpose. That design philosophy allowed $IREN to "re-purpose" its 50 MW Prince George data centers for its AI cloud operations by simply taking out $BTC mining ASICs and replacing them with GPU racks. Sure, to run cloud operations $IREN had to add back-up generators and other redundancy-purposed infrastructure at its sites, but that's merely a question of costs, not "development expertise". The core data center footprint has been developed in-house many years ago, not in "mid 2024" as you claim. It's also misleading to measure $IREN's build speed by anchoring to the start of its cloud operations and extrapolating from there. These are 2 completely different KPIs... Once Childress was fully ramped, $IREN proofed it could build 50 MW (gross) of air-cooled data center infrastructure in a timeframe of just 1 month. Then, if you account for the extra time needed to install back-up generators (for cloud) + installing the GPU racks, you land at roughly 2-3 months. That lands you at a build speed of ~17 MW / months. Admittedly, that's the speed for air-cooled deployments, not liquid cooled, which would take significantly longer to develop. But that's beside the point. You used an inherently flawed method to calculate "build speed" and paint a negative picture of $IREN relative to $NBIS. I don't think you did that on purpose, but you still got to be careful making these kinds of blunt statements. It's an easy way to loose credibility fast. What you calculated is still a valid KPI, but its not the same as "build speed". You effectively calculated how quickly $IREN scaled its existing cloud operations over the past years, relative to $NBIS. And yes, $IREN comes up short in that comparison. But why is that? As I demonstrated, $IREN is clearly not lacking in development speed, so why did they scale rather slowly? If you had been following the company for a whale, you'd know by now that $IREN is incredibly meticulous about timing hardware cycles. Management is executing the exact same playbook during its $BTC mining times... While most competitors over-commit to hardware that will soon be overshadowed by newer tech, $IREN scales slowly until it has the capacity to go 'all-in' at the start of a new hardware cycle. This strategy allowed $IREN to quickly emerge from merely a 'top 10' miner (by monthly $BTC output), to the number 1 operator in the space within a timeframe of just ~1 year. $IREN is following that exact same playbook today, but with AI hardware instead of mining ASICs. Instead of over-committing on H100/H200s, years after that GPU generation came out, $IREN took it slow, and focused instead on building out 100s of MW of data center infrastructure (both liquid & air-cooled) at its Childress (TX) campus. Today, the company is in a position in which it can casually purchase 50k units of new Blackwells (as it did last month), and become one of the fastest growing clouds in the sector. Likewise, we can observe the same pattern at $IREN's next flagship site: Sweetwater 1 (1.4 GW). Many investor seem to grow inpatient that management still hasn't signed large-scale deals for that new site yet, but $IREN is obviously just following the exact same strategy... This time with the Rubin GPU generation, which won't be produced at scale until H1 2027. There are several other reasons, that I haven't covered here, that make up $IREN's cycling strategy (such as financing, negotiating leverage, etc.), but the point remains. You can't make an apples to oranges comparison and label is as "facts". It's clear to me that your post is surface-level analayis at best... good for engagement, but not the type of content that will age very well. That said, based on your commentary, it seems like you have genuine interest in getting deeper into the $IREN rabbit hole. I hope my feedback is of some help in that regard. 🤝
English
25
37
433
86.3K